Quality Rating
The number of pieces inspected and accepted, divided by the number of pieces inspected, multiplied by 100.
Delivery Rating
Points derived by comparing the Promised Delivery Date to the Actual Receipt Date.
The total delivery points, divided by the total delivery points possible, multiplied by 100. Delivery points are assigned based on the following schedule:
100 Points - Receipt not exceeding one (1) day after the promised date.
97 Points - Receipt date 2 to 5 days after promised date.
95 Points - Receipt date 6 to 9 days after promised date.
93 Points - Receipt date 10 to 12 days after promised date.
85 Points - Receipt date 13 to 16 days after promised date.
80 Points - Receipt date 17 to 19 days after promised date.
70 Points - Receipt date 20 to 30 dates after promised date.
0 Points - All receipt dates 31 days or more after promised date.
Overall Supplier Performance Rating
Quality Rating multiplied by .5 + Delivery Rating multiplied by .5